In brief
Boracay has no power plants of its own; electricity reaches it from the mainland over a 69 kV line that includes a submarine cable. A 138 kV replacement, first targeted for March 2021, has an Energy Regulatory Commission deadline of 31 August 2026, and no source used here confirms it was finished by then.
- Supply: Boracay’s electricity comes from the Nabas substation on the mainland through a 69 kV overhead line and a submarine cable4.
- Project: the Nabas-Caticlan-Boracay 138 kV project was reported 93.161 percent complete in April 2026, with full completion targeted for August 20269.
- Delay: NGCP’s 2018 target was March 2021; the regulator moved the deadline from 31 May 2025 to 31 August 202616.
- Outages: at least 18 hours in May 2025 and about two to three days in September 202535.
- Price: AKELCO said in July 2026 that its residential rate would have risen by PHP 3.5695 per kWh without regulatory intervention11.
Disclosure: some links on this page are affiliate links, marked by the products, tours and hotels they name. A purchase through these links may earn the site a commission at no cost to you, and it never affects what is recommended. How this works.
Where to book Current rates across the island.
Frequently Asked Questions
Where does Boracay's electricity come from?
From the mainland. Boracay has no local power plants, and power arrives through a 69 kV line that includes a submarine cable from the Nabas substation34.
Is the new Boracay submarine cable finished?
Not confirmed. The ERC deadline is 31 August 2026, the project was 93.161 percent complete in April 2026, and no source used here reports it energized69.
Why did the project take so long?
The ERC cited site workability, right-of-way acquisition, procurement and other construction challenges when it moved the deadline from 31 May 2025 to 31 August 20266. NGCP’s 2018 target was March 20211.
Who runs Boracay's power?
AKELCO distributes power on the island3. NGCP operates transmission, including the Caticlan-Unidos 69 kV line it took over in November 20257.
Will electricity cost more in Boracay in 2026?
AKELCO said in July 2026 that its residential rate would have risen by PHP 3.5695 per kWh from June without intervention, and that staggered recovery was approved11. Check your bill or your host’s charges for the current amount.
How good is the internet on Boracay?
No independent speed test appears in the sources used here. nomads.com’s average is 10 Mbps, and the DICT secretary called access slow in 202217. See the remote-work page for the figures.
The detail
This page explains how power gets to Boracay, who runs each part of the chain, why the project meant to replace it is late, and what 2026 has brought in rates and grid shortages. The dated list of blackouts is in Boracay power outages in 2025 and 2026. Questions about hotel backup power are in Do Boracay hotels have backup generators?, and the remote-work view is in Working remotely from Boracay.
The short answer
| If you are… | Do this |
|---|---|
| Booking a stay | Treat a power cut as possible on any trip, and ask the property what it runs on backup power (see what to ask) |
| Working online while on the island | Plan for interruptions to power and mobile data; see remote work |
| Waiting for the new cable | Do not assume it is in service; no source used here reports it energized |
| Checking the grid on the day | AKELCO’s site shows a daily supply and demand table, not a list of advisories11 |
How the island is fed
Boracay has no local power plants, and the National Grid Corporation of the Philippines (NGCP) said in May 2025 that electricity reaches the island by submarine cable from the mainland3. In 2018 NGCP described the supply as “a single 69kV line” serving the island1. The Department of Energy (DOE) described the same arrangement in September 2025: Boracay and Caticlan draw power through a 69 kV overhead line and a submarine cable from the Nabas substation4.
Two organizations run the chain. The Aklan Electric Cooperative (AKELCO) is the local distributor3. NGCP operates transmission, and in November 2025 it took over the Caticlan-Unidos 69 kV line from AKELCO after the Energy Regulatory Commission (ERC) reclassified it as a transmission asset a year earlier7. The ERC order reported in October 2025 also covers the Avon-Caticlan 69 kV line, the Caticlan Cable Terminal Station and the Caticlan-Boracay submarine cable6.
The 2022 case for a second route was capacity. NGCP said the existing 69 kV submarine cable and overhead line “is no longer adequate to support load growth”, with demand projected at 102 MW by 2030 and 175 MW by 20402.
The 138 kV project, step by step
The Nabas-Caticlan-Boracay project adds a 138 kV line from Nabas to Caticlan, a 138 kV submarine cable from Caticlan to Boracay, an underground 69 kV line on the island, and upgraded substations1. It was announced as one project with one finish date, and the date has moved more than once.
| When | What was reported | Source |
|---|---|---|
| November 2018 | NGCP expected completion in March 2021; cost applied for at PHP 4.27 billion | 1 |
| November 2022 | Existing line judged inadequate; ERC-approved cost PHP 5.48 billion | 2 |
| December 2023 | Nabas substation operating | 9 |
| November 2024 | ERC reclassified the Caticlan-Unidos 69 kV line7; Power Philippines, in September 2025, reported that the ERC had ordered the project finished “within this year” | 74 |
| October 2025 | ERC moved the deadline from 31 May 2025 to 31 August 2026 and warned of “stricter scrutiny and potential penalties” | 6 |
| 21 November 2025 | NGCP takes over the Caticlan-Unidos line | 7 |
| 13 February 2026 | Rehabilitated Unidos-Caticlan 69 kV line energized | 8 |
| April 2026 | 93.161 percent complete; Boracay substation 80.25 percent; cable systems over 99 percent | 910 |
The reasons the ERC accepted for the extension were site workability, right-of-way acquisition and procurement, among other construction challenges6. In April 2026 the underground cable was targeted for June and the whole project for August 20269. The project is expected to serve over 155,000 residential, 13,000 commercial and 27 industrial customers9.
Sources disagree The reported cost differs by report: PHP 4.27 billion applied for in 20181, PHP 5.48 billion in 20222, PHP 4.23 billion in the October 2025 ERC extension report6 and PHP 5.27 billion in April 20269. Whether the figures count the same scope is not stated. For a traveller the cost does not matter; the completion date does.
Is it finished?
Not confirmed. The last status in the sources used here is April 2026, when the project was 93.161 percent complete, and NGCP again promised August 2026 in a Senate briefing on 28 May 2026 as reported by the Daily Tribune915. No source used here reports the 138 kV cable energized or the project completed by the 31 August 2026 deadline. Until one does, plan around the existing 69 kV supply.
What went wrong on the existing line
The old supply path failed twice in 2025, for different reasons. In May a broken cut-off jumper wire on the NGCP line at Nabas tripped the 69 kV Nabas-Unidos-Caticlan line, and Boracay lost power for at least 18 hours3. In September the line tripped again, and AKELCO traced the fault to arcing in underground 69 kV cables near the Caticlan Airport arrival area, caused by moisture intrusion and leakage4. An 800-meter temporary overhead bypass along the airport’s beachside perimeter restored supply45.
The bypass then had its own problems. NGCP named water-wave splash and salt-spray corrosion as the main cause of its recent failures and built an alternative bypass further from the shore, due to be energized in December 20257. When NGCP rehabilitated the line in early 2026 it found that about 88 percent of the identified defects were corrosion-related, from prolonged exposure to marine conditions8. The full dated list is in the outage timeline.
Rates and shortages in 2026
The 2026 story is shortage and price more than cable faults. At a Senate briefing on 28 May 2026, officials were reported to describe a capacity shortage on Panay of 87 MW, tied to a forced outage of a 150 MW unit15. On 8 July 2026 the Visayas grid went on red alert from 3 p.m. to 9 p.m., with 2,397 MW available against a 2,492 MW peak13. On 26 August 2026 the grid operator scheduled rotating brownouts from 1 p.m. to 11 p.m. with 293 MW short of demand, and AKELCO was among the cooperatives listed14. Neither GMA report says that Boracay itself lost power on those days.
AKELCO’s own site reports the cost side. At a stakeholders’ conference in July 2026 the cooperative said the residential rate would have reached PHP 15.6756 per kWh, PHP 3.5695 more than in June, without regulatory intervention. It put the cause down to higher Visayas demand, generating plants out of service and repeated Yellow and Red Alert declarations, and said the ERC had approved staggered recovery over several billing cycles11.
For context, GMA reported in June 2026 that MORE Power in Iloilo City raised its residential rate by PHP 2 to PHP 13.87 per kWh, and Negros Power in Bacolod by PHP 2.46 to PHP 13.84 per kWh, both citing higher spot-market purchases12. That report does not mention AKELCO, and AKELCO’s PHP 15.6756 is a no-intervention figure, so the numbers are not like for like. Short-stay visitors pay for electricity inside their room rate or resort charges; the rate matters most to anyone renting by the month.
Internet and mobile in short
No source used here gives an independent speed test for Boracay. What exists is dated and mixed. In August 2022 the secretary of the Department of Information and Communications Technology said on a visit that “Internet access is slow” on the island and planned a “WiFi For All” rollout, without giving speeds17. Converge launched fiber on Boracay in May 2023, and its chief executive said its offering was “much better than our competitors here”, a company claim16. Globe said in a release reported in May 2025 that it had more than 30 outdoor 5G sites on the island, also a company claim19. The National Telecommunications Commission registered Starlink in the Philippines in May 2022, with advertised speeds of 100 to 200 Mbps; the report is national and says nothing about Boracay18.
nomads.com’s own average for Boracay is 10 Mbps, covered with the other nomad figures in Working remotely from Boracay. SIM and eSIM rules for visitors are in SIM cards and eSIMs for Boracay.
Related Articles
Sources (19)
- NGCP spending P4.6 billion to reinforce Boracay transmission line — Philstar, 23 November 2018. Accessed 2026-10-03.
- NGCP works on Caticlan-Boracay line — BusinessMirror, reposted by Matuwid na Singil sa Kuryente, 16 November 2022. Accessed 2026-10-03.
- Blackouts hit Boracay, other Philippine tourist spots — Philstar, 12 May 2025. Accessed 2026-10-03.
- Boracay power outage spurs emergency bypass line work — Power Philippines, 14 September 2025. Accessed 2026-10-03.
- DOE restores power in Boracay after three-day outage from cable damage — Power Philippines, 15 September 2025. Accessed 2026-10-03.
- NGCP Gets ERC Approval to Extend Boracay Power Line Completion Deadline — Power Philippines, 13 October 2025. Accessed 2026-10-03.
- NGCP moves swiftly to restore, ensure power reliability in Aklan — Negros Now Daily, 22 December 2025. Accessed 2026-10-03.
- NGCP normalizes power in Aklan — Negros Now Daily, 26 February 2026. Accessed 2026-10-03.
- Department of Energy Philippines Inspects Nabas–Caticlan–Boracay Transmission Project to Strengthen Power Supply for Boracay Island — SolarQuarter, 16 April 2026. Accessed 2026-10-03.
- P5.27-B Aklan transmission project nearly complete — BusinessWorld, 16 April 2026. Accessed 2026-10-03.
- AKELCO, Aklan Electric Cooperative — AKELCO, July 2026 rate notice and daily supply and demand outlook, as seen 2026-10-03. Accessed 2026-10-03.
- Western Visayas power rates up in June 2026 — GMA News, 16 June 2026. Accessed 2026-10-03.
- NGCP: Red alert hoisted over Visayas grid on July 8, 2026 — GMA News, 8 July 2026. Accessed 2026-10-03.
- Rotating brownouts may hit Visayas consumers on Aug. 26, 2026 — GMA News, 26 August 2026. Accessed 2026-10-03.
- Loren, kinalampag ang energy at telco giants para sa Aklan at Antique — Daily Tribune, 29 May 2026. Accessed 2026-10-03.
- Converge ICT enters Boracay, ready to offer faster internet than rivals — Newsbytes.PH, 7 May 2023. Accessed 2026-10-03.
- DICT chief rues slow internet connection in Boracay island — Newsbytes.PH, 1 September 2022. Accessed 2026-10-03.
- NTC approves up to 200Mbps Starlink internet service entry in PH — Palawan Daily News, 27 May 2022. Accessed 2026-10-03.
- Globe boosts Boracay network amid tourism surge — Context.ph, 1 May 2025. Accessed 2026-10-03.